Archive for the ‘Bridge Expansion’ Category

bridge expansion >> driving piles and pouring piers

Friday, August 25th, 2017

When you go under a bridge, what do you see? Huge concrete columns – piers – that support it. The five-metre expansion of the bridge on Highway 7 West over Highway 400 is becoming fully visible as the new piers are completed. In the photo above you can see the three completed piers and crews pouring the concrete cap for the fourth.

Each one of these piers is held up with a set of nine piles. Piles are long poles driven straight down, until they reach a surface solid enough to hold everything above. In this case, the piles are each nine metres long.

In the photo, the tall piece of equipment beside the west abutment wall is the pile driver, which is – as you’d expect – used to drive the piles into the ground.

On top of the pile-supported-piers, there will be bridge footings, girders, and a wider deck to make room for cars and trucks – as well as buses on new vivaNext dedicated rapidway lanes and a multi-use path for pedestrians and cyclists.

While it’s true that piers are just a part of the bridge, the bridge is part of a road, which is part of a rapid transit system, which connects people to where they need to go.

Next time you go under a bridge, look at the piers that support it, and the engineering and construction that went into them.

We’re building rapid transit, and along the way making infrastructure – built to last.


For information on ongoing vivaNext projects, be sure to subscribe to email updates, and follow us on Twitter. Questions or comments? Comment below or email us at


the expansion of the Highway 400 bridge on Highway 7 West begins

Wednesday, July 26th, 2017

Many of you have already noticed the work that has begun on Highway 7 West at the bridge over Highway 400, so here’s an overview of the components of the newest mega-feat of engineering that you’ll see happening over the next few years.

The project is part of the Highway 7 West rapidway project in Woodbridge-Vaughan and it will include expanding the bridge – with the new segment added to the north side – by approximately 5 metres.

New piers

Construction includes four new piers to support the expansion, which means new foundations, footing and forms. With multiple lanes above and below, this is a complicated project and safety is paramount for both the travelling public and the workers on site.

Huge girder lift

In September, the first piece of a gigantic girder will be lifted into place. This girder, which is needed to support the expansion of the bridge, will be installed in five pieces.

Multi-use path and rapidway

What makes this project especially remarkable, is that it will not only include dedicated red-asphalt bus lanes, but a pedestrian and cycling path will be constructed in the centre of the bridge between the bus rapidway lanes. Once complete, the bridge will provide roadway and connections for all types of transportation modes.

Realigned ramps

That’s not all. In addition, two of the ramps on the east side of Highway 400 will be realigned in order to accommodate potential future development. And to accommodate the waterway conditions in the area, new culverts will be built under the new ramps.

You’ll be hearing much more about this massive undertaking as time goes on. Next month, we’ll look more closely at what’s involved in expanding the bridge itself – think piers, pile drivers and parapets!


For information on ongoing vivaNext projects, be sure to subscribe to email updates, and follow us on Twitter. Questions or comments? Comment below or email us at



a look back at the CN MacMillan Bridge expansion

Wednesday, July 12th, 2017

As work starts up on the Highway 7 bridge over Highway 400, which is being widened to accommodate rapidway lanes and a multi-use path, let’s take a look at a completed bridge expansion project: the CN MacMillan Bridge.

The Highway 7 bridge passes over the CN MacMillan Rail Yard, the second-biggest rail yard in Canada.

The expansion project, which was part of the Highway7 West-VMC rapidway project, involved widening the bridge by 8.5 metres to accommodate the two lanes of rapidway that opened in February 2017.

Crews poured 4,000 tonnes of concrete to build abutment walls, piers, foundation and piles, sidewalks and decks; embedded 300 tonnes of reinforcing steel; and built a new pedestrian sidewalk and hand-rail and bike lanes!

All of the work expanding the bridge had to be done – and was accomplished – without stopping the trains or impacting the 10 sets of tracks. For safety purposes, before construction even began, crews had to rehearse set-ups and take-downs with numerous safety drills so it would proceed like clockwork.

During construction, crews worked very closely with CN to coordinate work around train schedules. An additional challenge was the fact that the rail yard, which handles one-million-plus cars per year, also operates 24/7.

Mega feats of engineering and construction like the CN Bridge project are beginning again with the expansion of the Highway 7 west bridge over Highway 400. Next month, we’ll take a look at the different components of work involved for this project.

For information on ongoing vivaNext projects be sure to sign up for email updates, and follow us on Twitter. Questions or comments? Comment below or email us at