Categories
Construction Rapidways Uncategorized

check out the Keith Bridge progress

video - Davis Drive: Keith Bridge progress

It’s an exciting time for Newmarket as significant components of the Davis Drive rapidway project are beginning to take shape. Along with road widening and paving, construction of the first vivastation is underway at Parkside/Longford and Davis. As part of the vivaNext rapidway project on Davis Drive, the Keith Bridge is being completely reconstructed. Construction of the north side of the bridge is coming along and recently, the new bridge deck was poured with concrete. We’re excited to have captured part of the transformation!

The deck pour was originally scheduled to be a lengthy 16 hour operation, but to speed up the process our diligent crews brought in additional machines and completed the job in 8 hours – half the time. The pour was completed overnight, with crews working quickly and efficiently to minimize disruption to residents. Over 70 truckloads of concrete were pumped steadily into the form work of the bridge [similar to a mold]. Using what’s called a screed machine, the concrete was leveled out and smoothed to create a flat surface. Because the screed machine didn’t reach the outer edges of the bridge, workers expertly finished off the edges with hand trowels. Finally burlap and tarps were used to cover the poured concrete as part of the curing process. They were removed once the concrete set.

The bridge is on track to be completed by late 2014, and when finished it will include architectural features such as replica period light fixtures and poles, and decorative concrete railings that reflect Newmarket’s heritage. Check out the bridge pour video for yourself – after all, it’s not every day over 70 truckloads of concrete are poured in one continuous operation. Watch for more big moves as the transformation continues to unfold on Davis Drive!

 

Leave a Reply