Categories
Construction Stations

Winter work

Warden Station in Markham - Winter construction in 2010-2011

This winter has been unusually warm so far, but we probably can’t count on the balmy temperatures continuing all the way through until spring. But at the same time, our vivaNext rapidway construction schedule requires that we make good progress during winter. Although it might be surprising to see construction happening in winter, some work will be taking place – with a little modification to our warmer weather construction methods.

Over the winter, work continues along the boulevards on Highway 7 East, and we’ll build the foundations for the first three rapidway stations at West Beaver Creek Road, Leslie Street and East Beaver Creek Road.

Much of the work we’re doing involves concrete, which doesn’t actually dry but cures through its own internal chemical reaction that creates heat. If the concrete cools down too quickly, it won’t cure properly. So the crews must ensure the ground is warm enough before the concrete is placed, to enable the concrete to begin its own heating process. Once those chemical reactions get going, it keeps itself warm, and all we need to do is keep it insulated while it cures.

In areas where we need to excavate earth, we dig out the first few inches of frozen ground – with these milder temperatures the frost generally only extends down through the first six inches of soil. Then, using ground heaters, we blow hot air into the excavation to warm it up, and cover it with tarps. The concrete is then poured, and the tarps are kept on the concrete until it is cured. The concrete is tested to ensure it has properly set and meets our specifications.

By using these techniques, we will be able to continue work throughout the winter on the boulevards, and construct the six platforms at the three stations.

In the boulevards, we will continue to install the Cupolex® forms for the tree soil cells, which are excavated and then covered with concrete. On the station platforms, crews will augur shallow holes to pour the concrete caissons (foundations) for the platforms, then pour the concrete platform slabs on top of these foundations.

Plenty of work is happening this year for both Highway 7 East and Davis Drive, and there’s still lots of work left to do. But by continuing construction through the winter, we’ll be moving closer to finishing the Highway 7 rapidway.

2 replies on “Winter work”

Hi VIVAnext is there any update on the Viva Rapidways lane on Highway 7 and are still doing the LRT project I still want to know about that. thanks

DaleA: Hi Phillip,

On Highway 7 East, construction is over 22% complete, with the section of Highway 7 from Bayview to Highway 404 ready for crews to pour the foundations for new rapid transit stations. East of Highway 404 to Warden Avenue, utility relocation continues and roadway widening begins this year. Studies about the proposed LRT projects within the vivaNext rapid transit plan are on hold, until other related studies have been completed. Once those studies have concluded and it makes sense for us to resume, we will make such an announcement.

Hi Dale,

All of us living along the VIVA Blue line are surely deeply jealous of those that are going to enjoy the VIVA Purple on Highway 7 and the VIVA Blue extension along Davis Drive due to the VIVA only lanes coming onstream in the next couple of years. That’s also not to mention all the updates on this blog about it.

However, I do notice on the Rapidways page of VIVAnext’s website (http://www.vivanext.com/rapidways) that the timelines for construction for Yonge Street between Highway 7 and Major Mackenzie Drive say 2012 to 2015. This being 2012, when can those on VIVA Blue expect some action in 2012?

Perhaps an imagined timeline of what we can see over the next few years will let us on Yonge Street (the heart and sole of the VIVA system in numbers of passengers) feel less jealous of those mentioned earlier. I look forward to a VIVAnext blog post on this in the future.

DaleA: Hi Michael,

The procurement process to award the Yonge Street rapidway construction project to a contractor will start this spring and will take a few months to complete. Early construction activities may be underway this fall or winter – for example, soil testing and utility relocations.

Once awarded the project, the contractor will develop a schedule that we’ll share with the community.

Leave a Reply