Road paving at Warden & Enterprise

What type of work is being done?

Distinctive red asphalt will be paved on the rapidways (dedicated bus lanes).

Where exactly is this going on?

On the rapidways parallel to Warden Avenue on the west side and Enterprise Drive on the north side.

When will it start?

Saturday, November 6, 2010. (weather permitting)

How long will the work take?

One day – from 7 am to 5 pm

What impact will there be?

  • Northbound and southbound lane closures will take place throughout the day.
  • Southbound traffic on Warden Avenue will be shifted to share the northbound lanes from about Clegg Road to just south of Enterprise Drive in order to pave the southbound lanes of Warden Avenue.
  • Once the southbound side is complete, all traffic will be shifted to the west side of Warden Avenue to pave the northbound lanes of Warden Avenue.
  • The private roadway and ramp access to IBM will be blocked from 7 am to 5 pm. Access to IBM will be via Clegg Road for most of the day.
  • Police officers will be on site throughout the day to safely direct traffic as required.

Road Paving at Warden and Enterprise

be moved

When it comes to the future of transit in York Region – it’s coming to Markham this winter with the launch of the third section of the Highway 7 rapidway on South Town Centre Boulevard, Cedarland Road and Warden Avenue.

A lot of activity is taking place as we all prepare for Viva beginning to run in this new section of rapidway. This includes preparing to open the new Cedarland Station, testing of Viva and emergency service vehicles in the rapidway lanes and training of YRT/Viva staff – to name a few.

All this goes a long way to improving transit in York Region and providing a faster and more convenient commute. And all of you are a big part of that. Thank you!

Wondering what this is all about or what a rapidway is? Click here to find out.

....