Construction Bulletins: Davis Drive, Newmarket

 

Access to 130 Davis Drive temporarily closed from Parkside Drive - May 28, 2013

As crews continue to relocate underground storm pipes and drains on Davis Drive, they will be working in stages from the east side of Parkside Drive...
To learn more, please click here.


Visit the vivaNext project information centre on Davis Drive - May 23, 2013

We know construction is messy and the Davis Drive rapidway project is no exception. As construction continues...
To learn more, please click here.


Retaining wall construction at Bethel Church - May 14, 2013

Starting the week of May 13, crews will begin construction of two retaining walls in front of Bethel Church at 333 Davis Drive. This work is part of a larger project to...
To learn more, please click here.


 

Previous 2013 construction bulletins:

Preserving Newmarket's history - Relocating the Union Hotel - April 23, 2013

Utility manhole construction at 17555 Yonge Street - April 15, 2013

Retaining wall construction at 251-259 Davis Drive - April 12, 2013

200 Davis Drive - Entrance temporarily relocated off Parkside Drive - April 11, 2013

Retaining wall construction at 291 Davis Drive - April 2, 2013

Retaining wall construction resumes at 130 Davis Drive - March 28, 2013

Gas main installation on Davis Drive from Yonge Street to George Street - March 15, 2013

Lane reduction prepares Davis Drive for lots of construction activity - March 14, 2013

Temporary driveway narrowing at 230 Davis Drive - March 13, 2013

Keith Bridge widening on the north side - February 13, 2013

Retaining wall construction near 230 Davis Drive - February 1, 2013

Lane shift changes across from Southlake - February 1, 2013

 

2012 construction bulletins:

Culvert construction continues across from Southlake - December 14, 2012

Utility work at Yonge and Davis intersection - December 7, 2012

Keith Bridge lane shift - November 20, 2012

Culvert construction continues at KFC (655) and 665 Davis Drive- November 8, 2012

Davis Drive: Keith Bridge shifting toward completion- October 25, 2012

Utility manhole construction on Prospect Street south of Davis Drive- October 19, 2012

Work on sanitary lines at 470-474 Davis Drive- October 17, 2012

Retaining wall construction at 26 Lorne Avenue- September 17, 2012

Multiple lane closures west of Patterson Street- August 31, 2012

Water main work west of Patterson Street- August 11, 2012

Utility relocation at 390 Davis Drive- August 10, 2012

Tom Taylor Trail takes a new detour- August 3, 2012

Retaining wall construction at 693 Davis Drive- August 2, 2012

Retaining wall construction at the Dixon Medical Building (531 Davis Drive)- July 17, 2012

New gas main segment under the Holland River- July 13, 2012

Hydro relocation work on Davis Drive continues- June 28, 2012

Construction continues at Southlake Regional Health Centre - June 11, 2012

Hydro relocation work on Davis Drive - June 7, 2012

Retaining Wall construction at 446 Davis Drive - May 25, 2012

Retaining Wall construction at Southlake Regional Health Centre - May 22, 2012

Demolition at Parkside Drive and Davis Drive - May 11, 2012

Davis Drive: getting ready for construction - March 13, 2012

 

2011 construction bulletins:

Overnight construction on Main Street - November 6, 2011

Geotechnical testing on Davis Drive - October 3, 2011

Construction resumes at 16 - 18 Main Street - September 12, 2011

Nighttime lane closures on Davis Drive - August 30, 2011

Construction starting at 200 Davis Drive - August 18, 2011

Construction starting at 16 - 18 Main Street - August 3, 2011

Retaining wall construction begins at 130 Davis Drive - July 15, 2011

Retaining Wall Construction – 350 Davis Drive - June 10, 2011

Fencing vacant lots - June 6, 2011

Retaining Wall Construction – 20 & 54 Davis Drive - June 3, 2011

Keith Bridge construction continues - April 18, 2011

Retaining wall construction begins - March 18, 2011

Preparation for construction continues - March 4, 2011

Keith Bridge foundation construction begins - February 12, 2011

Davis Drive construction schedule – Spring 2011 - January 23, 2011

Keith Bridge widening begins - January 18, 2011

 

2009-2010 construction bulletins:

Tom Taylor Trail takes a detour - November 5, 2010

Demolition program continues on Davis Drive - October 20, 2010

Demolition program continues - September 29, 2010

Demolition program continues at 330 and 338 Davis Drive - August 10, 2010

Demolition program to begin on Davis Drive - August 3, 2010

Geotechnical investigations continue on Davis Drive - July 28, 2010

Archaeological assessment about to begin - May 13, 2010

Pre-construction work underway - March 19, 2010

Geotechnical investigation to take place on Davis Drive - November 20, 2009

Shop...we’re open

right_img

Helping to support local businesses as much as we can during construction, with the Shop7 and ShopDavis programs.

arrowfind out more

Community Liaisons

right_img

Nimisha Raja and Michelle Dudzik are your Community Liaisons. Whether you're a property owner, business operator, tenant or community group, they'll be happy to answer your questions.

arrowLearn more

Davis Drive public meeting materials

right_img

Find materials from open houses about the Davis Drive rapidway, all in one convenient location.

 

arrowGo there now

Rapidways

home bottom

arrowExplore

Subways

home bottom

arrowExplore

System Map

home bottom

arrowExplore

Copyright 2013 York Region Rapid Transit Corporation. All rights reserved.vivanext